Import and Export Projects

Blueprint already has import/export project feature between same versions of Blueprint, but we extended the support to migrate over processes from AgileRM over to new products.

Note: Currently system supports export from any 12.0-13.0 version of AgileRM to import to/from 5.3+ BluePrint version.

Steps to Migrate from old version to new version is as follows:

First navigate to Admin Portal.

How to Export
  1. Navigate to Projects > Select any desired project > Select either Full or Empty Export option.
  2. Click on Export.
  3. On Job Import/Export page > Check the Job export status.
  4. Download the package by clicking on download icon.
How to Import
  1. Select the project where project needs to be imported > Click on Import button
  2. Select the package , provide the project name and select the location.
  3. Click on Import
  4. Navigate to Job Imports/Exports tab to see the status