Import and Export Projects
Blueprint already has import/export project feature between same versions of Blueprint, but we extended the support to migrate over processes from AgileRM over to new products.
Steps to Migrate from old version to new version is as follows:
First navigate to Admin Portal.
How to Export
- Navigate to Projects > Select any desired project > Select either Full or Empty Export option.
- Click on Export.
- On Job Import/Export page > Check the Job export status.
- Download the package by clicking on download icon.
How to Import
- Select the project where project needs to be imported > Click on Import button
- Select the package , provide the project name and select the location.
- Click on Import
- Navigate to Job Imports/Exports tab to see the status